Tracked projects
1
Total MW
27.1 MW
Active pipeline
1
27.1 MW
Operational
0
0 MW
1 projects · regions: Humber
Status changed
6 Jul 2026
Status: operational → Status: approved
Status updated from PlanIt (https://planninganddevelopment.nelincs.gov.uk/online-applications/applicationDetails.do?keyVal=P5ZZ8QLJK3E00&activeTab=summary)
Source updated
6 Jul 2026
Decision: 2015-06-19 → Decision: 2018-04-18
Decision date updated from PlanIt (https://planninganddevelopment.nelincs.gov.uk/online-applications/applicationDetails.do?keyVal=P5ZZ8QLJK3E00&activeTab=summary)
Source updated
11 Jun 2026
Submitted: — → Submitted: 2015-03-05
Field submitted_date updated via admin editor
Source updated
11 Jun 2026
Decision: — → Decision: 2015-06-19
Field decision_date updated via admin editor
Source updated
11 Jun 2026
Energised: — → Energised: 2016-07-14
Field energised_date updated via admin editor